Project base line issue
In my sample project I have one sample Default Stream. In the stream I have 3 components.
Now i have created baselines in 3 components separately, Now i want to create a baseline for whole project that is based on 3 components baselines.
I known how to do the component baselines
But don't known how to create the project baselines based on components baselines, please help me with this it urgent for me...
Thanks
Now i have created baselines in 3 components separately, Now i want to create a baseline for whole project that is based on 3 components baselines.
I known how to do the component baselines
But don't known how to create the project baselines based on components baselines, please help me with this it urgent for me...
Thanks
One answer
Is a workspace snapshot what you want? From the doc:
Instructions on creating a workspace snapshot can also be found in the doc here.
A workspace snapshot provides a persistent record of the configuration of a workspace, expressed as a collection of component baselines.
Instructions on creating a workspace snapshot can also be found in the doc here.
Comments
I got what your are about say
but my doubt is, I have 2 components in a stream for two developers, and in that components i have made two initial baselines in each component.
Now i want to merge the two baselines to get my final project how to do that please...!
There is only one "initial baseline" for a component, i.e. the baseline that was created when that component was created. In order to merge two baselines, accept both of those baselines into your workspace, and then deliver the result to the stream.