Hi,
I want to populate fields in Planned for field. I am not able to see new iterations which I have added are reflecting in drop down box of Planned for field.
Anyone know how to make it visible? I have created 2 sub categories
e.g. Project
Testing
Cycle 1
Cycle 2 etc
I can only see Testing in Planned For field. I want to Populate Cycle 1 and Cycle 2 also.
Regards,
Prasad
Accepted answer
Please go through: https://jazz.net/library/article/589 . To see the iterations, you have to check the 'A release is planned for this iteration' check box. The Article above talks about this and several other things you need to know about the fundamental mechanism around work items.