Hi,

I want to populate fields in Planned for field. I am not able to see new iterations which I have added are reflecting in drop down box of Planned for field.

Anyone know how to make it visible? I have created 2 sub categories

e.g. Project

           Testing

                  Cycle 1

                  Cycle 2   etc

I can only see Testing in Planned For field. I want to Populate Cycle 1 and Cycle 2 also.

Regards,

Prasad

0 votes


Accepted answer

Permanent link
Please go through: https://jazz.net/library/article/589 . To see the iterations, you have to check the 'A release is planned for this iteration' check box. The Article above talks about this and several other things you need to know about the fundamental mechanism around work items.
Prasad Mandre selected this answer as the correct answer

0 votes

Comments

Thanks Ralph.

ThisĀ  change resolved my query . It helped .

Hi Prasad,

great! I would still recommend to read the article to avoid to run into similar situations. I found that a lot of users are not really aware of the relationships of the concepts in the beginning and waste a lot of time to get the required understanding. It was certainly that way for me.

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 6,128

Question asked: Feb 13 '13, 3:39 a.m.

Question was seen: 3,485 times

Last updated: Feb 13 '13, 9:19 a.m.

Confirmation Cancel Confirm