RPT Dashboard in RQM
2 answers
What kind of dashboard can we create for RPT or performance testing in RQM? I mean what kind of information shall we report?
Thanks
Jirong
OK, I don't see the RPT/RQM integration can provide much valuable information regarding the performance testing dashboard. So let me come out my own, how about we provide this to the managers:
Section1: SLA/Requirement/Objective
========================
Simple list of target numbers:
1. List of transactions to be tested
2. Response time for each transaction.
3. TPS
4. Active users.
Seection2: List of RPT Script/Schedule to be done
1. Script 1, 2, 3
2. Schedules 1,2,3
Highlight in green color for these are completed. So the manager can see how much work done and how much left.
Section3: Test/Schedule Run Result
1. Script validation - one user per script.
2. Baseline run - 5 user per script.
3. 50 users run.
4. 100 users run.
5 ...
6. 1000 users run.
Use color to indicate those are done.
Anything else should be in this report? This is more to report the progress of the performance testing to the non-technical management.
Thanks
Jirong
Currently there isn't any integration between RQM and RPT that is specific to such dashboard. However, RQM's dash board and reporting capabilities seem flexible enough for you to create such a dashboard.
You could use Test Case categories to identify which test case are meant for Performance Testing, then use these categories to filter data shown in RQM reports that show up on your performance dashboard.
I have heard talks about providing such integration between RPT and RQM by default, but nothing has been committed to a specific release.
You could use Test Case categories to identify which test case are meant for Performance Testing, then use these categories to filter data shown in RQM reports that show up on your performance dashboard.
I have heard talks about providing such integration between RPT and RQM by default, but nothing has been committed to a specific release.