How to I finish the last iteration in a timeline
Hello,
we have project that handles each release in an own iteration. Now we found that in some timelines the last iteration is still marked as current, even it is already worked down. How can I set the last iteration in a timeline to finished ? Thanks in advance. Sigi |
4 answers
Geoffrey Clemm (30.1k●3●30●35)
| answered Jan 24 '11, 6:08 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
You can't "unset" current. Being able to do so is requested in work
item 79007. Please feel free to add a comment to indicate your interest/support. Cheers Geoff On 1/24/2011 9:23 AM, oesterreicher wrote: Hello, |
I found a manual solution to handle this last leaf iteration problem in a timeline.
I did the following. Allocated an Iteration called "Finalize Iteration" as sibling to the last leaf iteration that should be closed. Set this iteration to the current, which set the prior last iteration to finished. Moved the "Finalize Iteration" to the next last leaf where I need it. Worked great. Sigi |
Ralph Schoon (63.1k●3●36●46)
| answered Jan 26 '11, 10:18 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Hi Sigi,
nice solution, thanks for sharing. Would you mind to add that as comment to work item 79007 mentioned by Geoff, so that we can track it as a work around? Thanks, Ralph I found a manual solution to handle this last leaf iteration problem in a timeline. |
Geoffrey Clemm (30.1k●3●30●35)
| answered Jan 26 '11, 7:08 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
One suggestion: In case you don't need any new iterations, just:
- move an iteration in from some other timeline into this timeline - mark that iteration current - move the iteration back to its original timeline I'll add this comment to 79007. Cheers, Geoff On 1/26/2011 10:23 AM, rschoon wrote: Hi Sigi, |
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.