Hello,

we have project that handles each release in an own iteration. Now we found that in some timelines the last iteration is still marked as current, even it is already worked down. How can I set the last iteration in a timeline to finished ?

Thanks in advance.
Sigi

0 votes



4 answers

Permanent link
You can't "unset" current. Being able to do so is requested in work
item 79007. Please feel free to add a comment to indicate your
interest/support.

Cheers
Geoff

On 1/24/2011 9:23 AM, oesterreicher wrote:
Hello,

we have project that handles each release in an own iteration. Now we
found that in some timelines the last iteration is still marked as
current, even it is already worked down. How can I set the last
iteration in a timeline to finished ?

Thanks in advance.
Sigi

0 votes


Permanent link
I found a manual solution to handle this last leaf iteration problem in a timeline.

I did the following.

Allocated an Iteration called "Finalize Iteration" as sibling to the last leaf iteration that should be closed.
Set this iteration to the current, which set the prior last iteration to finished.
Moved the "Finalize Iteration" to the next last leaf where I need it.

Worked great.

Sigi

0 votes


Permanent link
Hi Sigi,

nice solution, thanks for sharing. Would you mind to add that as comment to work item 79007 mentioned by Geoff, so that we can track it as a work around?

Thanks,

Ralph

I found a manual solution to handle this last leaf iteration problem in a timeline.

I did the following.

Allocated an Iteration called "Finalize Iteration" as sibling to the last leaf iteration that should be closed.
Set this iteration to the current, which set the prior last iteration to finished.
Moved the "Finalize Iteration" to the next last leaf where I need it.

Worked great.

Sigi

0 votes


Permanent link
One suggestion: In case you don't need any new iterations, just:
- move an iteration in from some other timeline into this timeline
- mark that iteration current
- move the iteration back to its original timeline

I'll add this comment to 79007.

Cheers,
Geoff

On 1/26/2011 10:23 AM, rschoon wrote:
Hi Sigi,

nice solution, thanks for sharing. Would you mind to add that as
comment to work item 79007 mentioned by Geoff, so that we can track
it as a work around?

Thanks,

Ralph

oesterreicherwrote:
I found a manual solution to handle this last leaf iteration problem
in a timeline.

I did the following.

Allocated an Iteration called "Finalize Iteration" as
sibling to the last leaf iteration that should be closed.
Set this iteration to the current, which set the prior last
iteration to finished.
Moved the "Finalize Iteration" to the next last leaf where
I need it.

Worked great.

Sigi

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Jan 24 '11, 9:16 a.m.

Question was seen: 6,068 times

Last updated: Jan 24 '11, 9:16 a.m.

Confirmation Cancel Confirm