It's all about the answers!

Ask a question

Duration based planning in RTC v3


Hideaki Hata (643) | asked Nov 12 '10, 12:15 a.m.
I'm using RTC v3 RC1.
When I make WBS with traditional planning feature, effort based planning is adopted.
Can we change the planning mode from effort based to duration based???

(effort based planning)
-each tasks(work items) must have effort hours for each resources
-task start/finish date will be calculated according to the effort of each tasks

(duration based planning)
-each tasks will have start/finish date
-task start/finish date will be calculated by each task's start/finish date and dependencies
-effort is not considered when calculating the date

*these two types of planning were supported by RPM(Rational Portfolio Manager) and MSP also supports similar feature.

Be the first one to answer this question!


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.