Cross Project Workload Reporting
![]()
Is there a way in RTC to report workload across multiple projects?
|
3 answers
![]()
Any updates so far?
-thanks in advance |
![]()
Geoffrey Clemm (30.1k●3●30●35)
| answered Mar 29 '12, 8:17 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
The work item for this is 94056. It is not currently scheduled for a release. Please feel free to add a comment to that work item indicating your interest/support.
Some initial progress in this direction is being made in RTC-4.0, by allowing you to reference a work item in another plan, and have it affect the schedule. The details can be found in work item 169425. Any updates so far? |
![]()
Thanks a lot, Geoffrey!
Do you know what CCM/JTS database tables should I query to create this report? -thanks in advance |
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.