How customizable is the "Burn Down" report


James Leone (13613513) | asked Jul 06 '10, 5:46 p.m.
Hello,

Is it possible to have the burn-down report exclude weekend days and other non-working days?

Somewhat related, is there a way to establish a "baseline" burn-down projection that will continually appear on the chart and will serve as visual guidance as to the quality of our original burn-down estimates vs. the actual burn down progress that took place during the sprint itself?

One answer



permanent link
James Moody (3.3k24) | answered Jul 13 '10, 11:34 a.m.
JAZZ DEVELOPER
On 7/6/2010 5:52 PM, jleone wrote:
Hello,

Is it possible to have the burn-down report exclude weekend days and
other non-working days?

This isn't possible at the moment. Seems like a simple change, but our
burndown report is currently a continuous time axis, rather than one
data point per day, so omitting days is much more difficult than one
might imagine

Somewhat related, is there a way to establish a "baseline"
burn-down projection that will continually appear on the chart and
will serve as visual guidance as to the quality of our original
burn-down estimates vs. the actual burn down progress that took place
during the sprint itself?

What kind of baseline? Are you talking about an "ideal" line from top
left to bottom right?

james
RTC Reports Team Lead