Hello

Under what circumstances do change sets show up in a Work Item ("Links" tab, "Change Sets" section)?

I do have change sets that were associated with a particular Work Item when checked-in and delivered, but they are not referenced in this section.

Thanks! Martin

0 votes


Accepted answer

Permanent link
Sorry, update to answer my own question: It turns out one needs patience: It took about 30 Minutes for the change set to turn up, but now it's there.
David Lafreniere selected this answer as the correct answer

0 votes

Comments

I would guess that the change set would have shown up immediately had
you clicked the refresh button on the work item. (But I could be
wrong.) In my experience, any change that affects the work item that
you make from within your Eclipse workspace is immediately reflected in
the work item editor. But changes made elsewhere don't show up until
some amount of time passes or until you click refresh.

Sorry, I should have mentioned that I tried to refresh: That was actually what was confusing me, because in all other areas of Team Concert "refresh" does work.
In this particular case it seems that there is a background process running on the server which builds up all the reverse tracability links.

Regards, Martin

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,019
× 1,202
× 149
× 102

Question asked: Dec 10 '09, 4:56 a.m.

Question was seen: 6,337 times

Last updated: Aug 02 '16, 8:23 p.m.

Confirmation Cancel Confirm