Hello

Under what circumstances do change sets show up in a Work Item ("Links" tab, "Change Sets" section)?

I do have change sets that were associated with a particular Work Item when checked-in and delivered, but they are not referenced in this section.

Thanks! Martin

Accepted answer


permanent link
Martin Erzberger (131199) | answered Dec 10 '09, 4:59 a.m.
Sorry, update to answer my own question: It turns out one needs patience: It took about 30 Minutes for the change set to turn up, but now it's there.
David Lafreniere selected this answer as the correct answer

Comments
David Olsen commented Dec 10 '09, 10:38 p.m. | edited Aug 02 '16, 8:19 p.m.
JAZZ DEVELOPER

I would guess that the change set would have shown up immediately had
you clicked the refresh button on the work item. (But I could be
wrong.) In my experience, any change that affects the work item that
you make from within your Eclipse workspace is immediately reflected in
the work item editor. But changes made elsewhere don't show up until
some amount of time passes or until you click refresh.


Martin Erzberger commented Dec 15 '09, 8:35 a.m. | edited Aug 02 '16, 8:23 p.m.

Sorry, I should have mentioned that I tried to refresh: That was actually what was confusing me, because in all other areas of Team Concert "refresh" does work.
In this particular case it seems that there is a background process running on the server which builds up all the reverse tracability links.

Regards, Martin