How to generate report including changes between two baselines in DNG/RM project

Procedure to generate report including changes between two baselines in DNG/RM project

0 votes



One answer

Permanent link
You cannot generate a document that shows changes between 2 baselines in DNG. One solution is to generate 2 versions of the document and then compare them using MS Word as explained in https://rpeactual.com/2016/10/26/document-comparison-between-configurations-or-versions-or-views/

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,019

Question asked: Dec 05 '16, 12:16 a.m.

Question was seen: 1,910 times

Last updated: Dec 05 '16, 12:49 a.m.

Confirmation Cancel Confirm