It's all about the answers!

Ask a question

How to generate report including changes between two baselines in DNG/RM project


Vani B (1391275) | asked Dec 05 '16, 12:16 a.m.
Procedure to generate report including changes between two baselines in DNG/RM project

One answer



permanent link
Subramanya Prasad Pilar (4.6k16) | answered Dec 05 '16, 12:49 a.m.
You cannot generate a document that shows changes between 2 baselines in DNG. One solution is to generate 2 versions of the document and then compare them using MS Word as explained in https://rpeactual.com/2016/10/26/document-comparison-between-configurations-or-versions-or-views/

Your answer


Register or to post your answer.