It's all about the answers!

Ask a question

How to generate report including changes between two baselines in DNG/RM project


Vani B (1391067) | asked Dec 05 '16, 12:16 a.m.
Procedure to generate report including changes between two baselines in DNG/RM project

One answer



permanent link
Subramanya Prasad Pilar (4.6k16) | answered Dec 05 '16, 12:49 a.m.
You cannot generate a document that shows changes between 2 baselines in DNG. One solution is to generate 2 versions of the document and then compare them using MS Word as explained in https://rpeactual.com/2016/10/26/document-comparison-between-configurations-or-versions-or-views/

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.