Jazz Forum Welcome to the Jazz Community Forum Connect and collaborate with IBM Engineering experts and users

How to get the Risk Matrix Diagram in SCRUM?

Hi,

We will have risk matrix in formal, i want to have the same risk matrix attribute in scrum project also. the project area is already created and there are many customized workitems. is it possible to get it in the running project area?


Thanks,
Praveen

0 votes



One answer

Permanent link
  Hi Praveen,

yes, it is. In the project administrative area you can create a new work item type called "risk" and add the same attributes that the formal work item have (including the risk matrix). If the work item with this name already exist, you can update it and add the matrix. You can do that even if the project area is already running.

The risk matrix is a Non-Attribute-based presentation. You can find it in the list.

Maybe this can help: https://jazz.net/library/article/1003/

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 1,221

Question asked: Mar 30 '16, 5:35 a.m.

Question was seen: 2,442 times

Last updated: Mar 30 '16, 7:38 a.m.

Confirmation Cancel Confirm