It's all about the answers!

Ask a question

How to sum estimation time of all the childeren task ?


Vikash Singh (422665) | asked Aug 04 '15, 2:22 a.m.

I have one task and some child task ,I would like to automatically sume all the estimated time of child task.

Please guide me. 

One answer



permanent link
Ralph Schoon (63.1k33645) | answered Aug 04 '15, 2:27 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
In plans the plan does it for you.

This is the only way I am aware of to extend RTC: https://rsjazz.wordpress.com/2012/07/31/rtc-update-parent-duration-estimation-and-effort-participant/


Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.