How to sum estimation time of all the childeren task ?


Vikash Singh (423065) | asked Aug 04 '15, 2:22 a.m.

I have one task and some child task ,I would like to automatically sume all the estimated time of child task.

Please guide me. 

One answer



permanent link
Ralph Schoon (63.6k33646) | answered Aug 04 '15, 2:27 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
In plans the plan does it for you.

This is the only way I am aware of to extend RTC: https://rsjazz.wordpress.com/2012/07/31/rtc-update-parent-duration-estimation-and-effort-participant/