Module Baselines


Cld Zmu (211) | asked Jul 24 '15, 4:15 p.m.

Hello,

I am using version 5.0.1.

I am trying to figure out a way to do versioning on DOORS. Is building a module baseline the only way I can do versioning? Also, if creating a module baseline is indeed the only way, would I need to create a new module baseline every single time I make a change to my requirements document? If this is so, do you have any suggestions on how to manage all these versions that I would be creating?

Lastly, how do I compare the changes I have made on previous modules?

Thank you in advance,

One answer



permanent link
Donald Nong (14.5k314) | answered Jul 27 '15, 3:13 a.m.
All you are looking for is the new "configuration management" introduced in RDNG 6.0. With RDNG 5.0.1, you can only have project baselines and module baselines.