Uma venkata Lekkala (52819) | asked May 07 '15, 5:25 p.m.
 I assigned some tasks to members of a team in sprint backlog plan. They have 0 hrs and estimates are showing in red. How to allocate hours?

Accepted answer


permanent link
Ralph Schoon (63.5k33646) | answered May 12 '15, 3:34 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
On the user's profile (in the CCM application, not JTS), in the Work Environment. Assign a percentage to the team area/project area.

The user must be in the team area to show available hours as far as I can tell.




Uma venkata Lekkala selected this answer as the correct answer

Comments
Uma venkata Lekkala commented May 12 '15, 12:14 p.m.

  Thanks, That's exactly what I needed!