How to add hours to resource in RTC?
I assigned some tasks to members of a team in sprint backlog plan. They have 0 hrs and estimates are showing in red. How to allocate hours?
|
Accepted answer
Ralph Schoon (63.5k●3●36●46)
| answered May 12 '15, 3:34 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
On the user's profile (in the CCM application, not JTS), in the Work Environment. Assign a percentage to the team area/project area.
The user must be in the team area to show available hours as far as I can tell. Uma venkata Lekkala selected this answer as the correct answer
|