Jazz Forum Welcome to the Jazz Community Forum Connect and collaborate with IBM Engineering experts and users

How to add hours to resource in RTC?

 I assigned some tasks to members of a team in sprint backlog plan. They have 0 hrs and estimates are showing in red. How to allocate hours?

0 votes


Accepted answer

Permanent link
On the user's profile (in the CCM application, not JTS), in the Work Environment. Assign a percentage to the team area/project area.

The user must be in the team area to show available hours as far as I can tell.




Uma venkata Lekkala selected this answer as the correct answer

0 votes

Comments

  Thanks, That's exactly what I needed!

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 6,131

Question asked: May 07 '15, 5:25 p.m.

Question was seen: 2,299 times

Last updated: May 12 '15, 12:14 p.m.

Confirmation Cancel Confirm