How can you have multiple current iterations?

 We have multiple releases going in a project area each with a separate timeline with different iterations.  How can we use the current iteration in this scenario so we can filter TCERs that are due for the "current iteration" in views

0 votes

Comments

there is a current iteration per timeline.  so you will need to specify the timeline first..  many tools don't deal with this easily.



One answer

Permanent link
Hi David,

I would suggest to -
1. Create different Team Areas within the project area and assign the timeline to each team area.
2. Enable team areas and support for multiple timelines in RQM Web Browser. To do this, go to Settings -> Manage Project Properties -> Team Areas and Timelines.
3. Create a test plan for each release and assign appropriate team area to the test plan. In a "Test Schedules" section of the test plan, now you can associate the team area time line with the test plan.
4. Create TCERs for the iterations associated with the test plan.

For more details please see RQM Help doc link - Setting up timelines, iterations, and team areas

Thanks,
Vijay

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 1,222

Question asked: Aug 20 '14, 4:20 p.m.

Question was seen: 5,139 times

Last updated: Aug 26 '14, 3:28 a.m.

Confirmation Cancel Confirm