Error when importing XML MPP Plan into RTC 4.0.4 when choosing to mark tasks as completed
Hi,
we are using RTC 4.0.4. When trying to import a new MPP XML Plan into RTC, and choosing to mark tasks as completed in the wizzard, import is failing with error: Cannot save work item '14200' because its parent work item '14272' is resolved. Looks like a timing issue, is this as expected?
Regards,
Lorena Almela
we are using RTC 4.0.4. When trying to import a new MPP XML Plan into RTC, and choosing to mark tasks as completed in the wizzard, import is failing with error: Cannot save work item '14200' because its parent work item '14272' is resolved. Looks like a timing issue, is this as expected?
Regards,
Lorena Almela