Plan view - Viewing current state - time remaining
Hi ,
I am using jazz 1.0.1.1 , in the plan view I would like to be able to see the current state of the plan , not just the design . Is it possible to configure the view to present the time remaining or the time spent depends on the project configuration? |
One answer
abaror wrote:
Hi , No, in RTC 1.0.1.1 this is not possible. For RTC 2.0 we implemented configurable columns which allow you to display any attribute you like. -- Cheers, Johannes Agile Planning Team |