Assign iteration to a WI template in Project initialization.


Pablo Silva (16157) | asked Jan 20 '14, 10:44 a.m.
edited Jan 20 '14, 1:31 p.m.
So , we have a fixed number of tasks that have to be done always, and i need to assign them to a specific iteration on the project area initialization.
On the process specification syntax wiki i didn't found the attribute to assing the WI to an iteration.

I'm using CLM 4.0.4

Do you guys have any ideas !?
Thanks.

Comments
sam detweiler commented Jan 20 '14, 7:57 p.m.

that is the Planned For attribute


Pablo Silva commented Jan 21 '14, 7:54 a.m.

yes, but on the work item template initialization (XML) how do you call that same attribute ??

2 answers



permanent link
sam detweiler (12.5k6195201) | answered Jan 21 '14, 8:28 a.m.

Comments
Pablo Silva commented Jan 21 '14, 9:35 a.m.

Thanks for the answer Sam , i will try it out later today , ill get you back the the results.
Best regards.


permanent link
Renzo Disi (122) | answered Jan 22 '14, 6:16 p.m.
Above mentioned label <rtc_cm:plannedfor is OSCL format to consult for an existing WI.

Here is part of XML used to configure initialization.  Thing is that there is no documentation for workitem label in order to know how initialize plannedFor attribute (or others).


===============

<project-configuration><initialization><server-initialization><followup-actions><followup-action .....
  <workspace....<workitems><category......
<workitem
type="task"
categoryPath="Category 1"