Scorecard Report - How do I define a milestone
Trying to get a simple metrics out of RQM for score card. Can someone please explain how I can create a test milestone. I thought it was tied to Test Schedule, however, the dialog that shows the test milestone for a scorecard is still not showing the test Schedule I've created. Thanks Amir |
One answer
Hi, Amir,
The test milestone of test plan in report is the test schedule of test plan on web. The Scorecard report is not a live report and it is a report fetching data from data warehouse. Please make sure you have configured the data warehouse and run the data collection jobs after your change, then you would see the test milestone in the report. |