Hi,
i reused a work items which was a user story. As a user stroy I had assigned story pounts to it. When I reused the story, I changed it to become a task. The task doe snot have stroy points, but when it shows up in a query it now shows the old story points :( . I guess that is not intended?

0 votes



One answer

Permanent link
Hi
This is the way it works right now. Attributes are added to the work item on type change, but they are not removed (this also has advantages s.t. when changing the type back to story, the points are still there).
The following work item tracks the possibility to archive such attributes:
https://jazz.net/jazz/resource/itemName/com.ibm.team.workitem.WorkItem/59558

Regards

Marcel
Jazz Work Item team

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Dec 02 '08, 10:55 a.m.

Question was seen: 3,721 times

Last updated: Dec 02 '08, 10:55 a.m.

Confirmation Cancel Confirm