reuse of work items leads to wrong data in work item


Astrid Kreissig (3164) | asked Dec 02 '08, 10:55 a.m.
Hi,
i reused a work items which was a user story. As a user stroy I had assigned story pounts to it. When I reused the story, I changed it to become a task. The task doe snot have stroy points, but when it shows up in a query it now shows the old story points :( . I guess that is not intended?

One answer



permanent link
Marcel Bihr, Jazz Work Item team (1.4k) | answered Dec 03 '08, 3:25 a.m.
JAZZ DEVELOPER
Hi
This is the way it works right now. Attributes are added to the work item on type change, but they are not removed (this also has advantages s.t. when changing the type back to story, the points are still there).
The following work item tracks the possibility to archive such attributes:
https://jazz.net/jazz/resource/itemName/com.ibm.team.workitem.WorkItem/59558

Regards

Marcel