It's all about the answers!

Ask a question

How do I control what state groups are columns in a Taskboard?


Erwin Kunz (94687086) | asked Jul 05 '12, 5:20 a.m.
retagged Dec 07 '12, 1:45 a.m. by Nhi P Ta (18841018)

Hi

I would like to create a new state group Implemented in between of In Progress and Closed

for epics and story but not for Tasks

But "unfortunately" the state group are system wide and not per Work Item Type.

And so the new state group appears on the Taskboard, also there is no execution item state belonging to this new group.

I there a way to "hide" this new state group from the taskboard, or remove it from the execution items workflows?

Thanks you

erwin


Comments
Geoffrey Clemm commented Jul 05 '12, 9:35 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER

To understand your use case better, why are you creating an "Implementation" state group?


Erwin Kunz commented Jul 05 '12, 10:01 a.m. | edited Jul 05 '12, 10:02 a.m.

Hi Geoffrey

The initial use case is reporting. To be able to have one report valid for whatever work items, we thought using State Groups for our queries; instead of having to check the different states

I've a drawing I would share, but no idea how to put that here

Thank you

erwin


Geoffrey Clemm commented Jul 05 '12, 10:19 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER

Yes, that all makes sense.

Accepted answer


permanent link
Geoffrey Clemm (30.1k33035) | answered Jul 05 '12, 10:18 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER

This is not currently supported.  I've submitted work item 216786 Allow control of what state groups are used as Taskboard columns (216786) requesting this functionality.

Ralph Schoon selected this answer as the correct answer