How do I control what state groups are columns in a Taskboard?

Hi

I would like to create a new state group Implemented in between of In Progress and Closed

for epics and story but not for Tasks

But "unfortunately" the state group are system wide and not per Work Item Type.

And so the new state group appears on the Taskboard, also there is no execution item state belonging to this new group.

I there a way to "hide" this new state group from the taskboard, or remove it from the execution items workflows?

Thanks you

erwin

0 votes

Comments

To understand your use case better, why are you creating an "Implementation" state group?

Hi Geoffrey

The initial use case is reporting. To be able to have one report valid for whatever work items, we thought using State Groups for our queries; instead of having to check the different states

I've a drawing I would share, but no idea how to put that here

Thank you

erwin

Yes, that all makes sense.


Accepted answer

Permanent link

This is not currently supported.  I've submitted work item 216786 Allow control of what state groups are used as Taskboard columns (216786) requesting this functionality.

Ralph Schoon selected this answer as the correct answer

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 6,131

Question asked: Jul 05 '12, 5:20 a.m.

Question was seen: 4,581 times

Last updated: Dec 07 '12, 1:45 a.m.

Confirmation Cancel Confirm