Hi All,

I am using Agile@scale template (https://www-304.ibm.com/support/docview.wss?uid=swg24028581) and great to see "Time Tracking" feature on the work items.


Is that possible to import the "Time Tracking" feature to an existing Scrum template project?

Cheers,
Simon

0 votes



6 answers

Permanent link
Have you migrated to a version that supports time tracking? Have you tried to configure TimeTracking in the Planning section of the process configuration?

I am just wondering, I think I migrated several projects and never noticed that time tracking was not available after migration. I might have overlooked that.

0 votes


Permanent link
Hi,

I have created a new project area based on Agile@scale template and planning to import the "Time Tracking" feature to an existing scrum template.

Time tracking is to play around an builtin attribute named "Time Spent".

Cheers,
Simon


Have you migrated to a version that supports time tracking? Have you tried to configure TimeTracking in the Planning section of the process configuration?

I am just wondering, I think I migrated several projects and never noticed that time tracking was not available after migration. I might have overlooked that.

0 votes


Permanent link
Hi,

you can't typically "Import" a process into an existing project area.

If time tracking requires that there is a time spent attribute with ID 'com.ibm.team.workitem.attribute.timespent' what you could try is to add that attribute to your work items (if the don't already have it) and see of that works.

0 votes


Permanent link
Thanks a lot."Time Spent" attribute is already avilable on the Defect WI in scrum template. I tried to create a new tab/section similar to Agile@scale template, but when I save the changes, those new additions are not reflected. Its not getting saved properly.

Cheers,
Simon


Hi,

you can't typically "Import" a process into an existing project area.

If time tracking requires that there is a time spent attribute with ID 'com.ibm.team.workitem.attribute.timespent' what you could try is to add that attribute to your work items (if the don't already have it) and see of that works.

0 votes


Permanent link
Take a look at the section 4 "Optional: To enable time tracking in
default and task work items"

http://publib.boulder.ibm.com/infocenter/clmhelp/v3r0m1/topic/com.ibm.team.platform.doc/topics/t_customize_template_formal_features.html

You will need to paste the XML contents in the appopriate sections in
the XML process template.

josthi wrote:
Thanks a lot."Time Spent" attribute is already avilable on
the Defect WI in scrum template. I tried to create a new tab/section
similar to Agile@scale template, but when I save the changes, those
new additions are not reflected. Its not getting saved properly.

Cheers,
Simon


rschoonwrote:
Hi,

you can't typically "Import" a process into an existing
project area.

If time tracking requires that there is a time spent attribute with
ID 'com.ibm.team.workitem.attribute.timespent' what you could try is
to add that attribute to your work items (if the don't already have
it) and see of that works.



--
Boris Kuschel
Jazz Jumpstart Team - IBM Software, Rational

0 votes


Permanent link
Hi Kuschel,

Thank you very much. It worked.

Cheers,
Simon


Take a look at the section 4 "Optional: To enable time tracking in
default and task work items"

http://publib.boulder.ibm.com/infocenter/clmhelp/v3r0m1/topic/com.ibm.team.platform.doc/topics/t_customize_template_formal_features.html

You will need to paste the XML contents in the appopriate sections in
the XML process template.

josthi wrote:
Thanks a lot."Time Spent" attribute is already avilable on
the Defect WI in scrum template. I tried to create a new tab/section
similar to Agile@scale template, but when I save the changes, those
new additions are not reflected. Its not getting saved properly.

Cheers,
Simon


rschoonwrote:
Hi,

you can't typically "Import" a process into an existing
project area.

If time tracking requires that there is a time spent attribute with
ID 'com.ibm.team.workitem.attribute.timespent' what you could try is
to add that attribute to your work items (if the don't already have
it) and see of that works.



--
Boris Kuschel
Jazz Jumpstart Team - IBM Software, Rational

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 10,952

Question asked: Feb 13 '12, 12:21 p.m.

Question was seen: 6,866 times

Last updated: Feb 13 '12, 12:21 p.m.

Confirmation Cancel Confirm