Jazz Forum Welcome to the Jazz Community Forum Connect and collaborate with IBM Engineering experts and users

Is it possible to automate timeline advancement in RTC?

We have RTC timelines configured and we have been manually advancing the timeline at the end of each sprint.  Is there a way to automate this?  It seems like since the timelines are fully defined, RTC should be able to auto-advance the timeline to the next iteration.

We are on version 6.0.6.1 iFix003.

0 votes



2 answers

Permanent link

 See work item: https://jazz.net/jazz/web/projects/Rational%20Team%20Concert#action=com.ibm.team.workitem.viewWorkItem&id=88813

Until that is implemented, you would need to write a custom API-based tool to perform the update.

0 votes

Comments

Do not call that a 'script' Geoff. Basically one would need to create a custom API based tool.


Permanent link
Even if this were possible I wouldn't recommend it.

The reason this is a manual process is because in reality there will always be some overlap between the end of one sprint and the start of the next, even if it's just tidying up and closing off work items. You want to be able to do this against the assigned sprint, and then make the next one the default.

I make it part of the retrospective to officially close off and progress the plan - becomes part of the routine then

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,026

Question asked: Sep 19 '19, 6:15 p.m.

Question was seen: 2,015 times

Last updated: Sep 22 '19, 8:45 p.m.

Confirmation Cancel Confirm