Is it possible for us to copy/move the quick planner boards from one server to another?
Accepted answer
Hello Maria, by "migrating" you mean that the work items are being exported - imported to a new server, or the whole server along its database is being migrated to a new CLM installation? If the first option is what you are doing unfortunately the quick planner boards are not exportable. If the second option is what's going on then boards are part of the project area and should be migrated along with the other data from the database.