Moving Story items from one Sprint to other Sprint

Hi

I would like to know if any one has had experience of moving Story item from one Sprint to other Sprint. For e.g a Story might be deferred from Sprint 1 to Sprint 2.

So in Sprint 1 the TASKS linked to the Story would have burned few hours. SO how will RTC take care of the TASKS when it is Planned for Sprint 2 in terms of progress or load?

Regards

Niranjan V

0 votes


Accepted answer

Permanent link
The time spent is moved to Sprint 2. But there is a function in Eclipse client "Continue work in" and which closes current workitem and creates a new one with corrected estimate or time spent. I am not sure how it works for story points thus.
V Niranjan selected this answer as the correct answer

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details
× 12,019

Question asked: Jul 29 '15, 9:18 p.m.

Question was seen: 2,737 times

Last updated: Jul 30 '15, 6:07 a.m.

Confirmation Cancel Confirm