Moving Story items from one Sprint to other Sprint
Hi I would like to know if any one has had experience of moving Story item from one Sprint to other Sprint. For e.g a Story might be deferred from Sprint 1 to Sprint 2. So in Sprint 1 the TASKS linked to the Story would have burned few hours. SO how will RTC take care of the TASKS when it is Planned for Sprint 2 in terms of progress or load? Regards Niranjan V
|
Accepted answer
The time spent is moved to Sprint 2. But there is a function in Eclipse client "Continue work in" and which closes current workitem and creates a new one with corrected estimate or time spent. I am not sure how it works for story points thus.
V Niranjan selected this answer as the correct answer
|