RTC and Team Planning
We are in the face of introducing RTC in our environment. In the situation where we are offering SCRUM template to a particular development team, like any other large organisation we always have to face the long term planning/commitment aspect as well.
Can anyone of you share us any hints, that would enable to us have a velocity based planning (projection) for a scrum team in RTC?
We would like to know whether such a possibility is existing in RTC or not? If yes, how to use it.
Scenario:
Scrum team with backlog of stories
All stories in the backlog has a story point assigned (estimation)
All stories are also Ranked
Output expected:
A projection for a story in the backlog, which tells approximately when this story can be delivered by the team
Can be in a dashboard or any other report
Assumption:
Team velocity is available from the past iterations (or using team capacity and allocation)
Thank you very much.
2 answers
http://www-01.ibm.com/support/knowledgecenter/SSYMRC_5.0.1/com.ibm.team.reports.doc/topics/c_ccm_check_velocity.html?lang=en
Just keep in mind you may have to customize the RTC instance based on your needs. This is documented throughout jazz.net and the information center as well.