Wrong "Total Hours Available"
Hello,
One of my team members has a wrong number presented (7, when in fact should be ~670) in the "total hours available", when looking at a version plan, viewed as "breakdown load".
We have checked that the work days are correctly configured and we cannot seem to understand why this is happening.
Rest of the team members has the correct "total hours available" and this is the first time we experience such problem (though we used RTC for previous releases too).
Can you offer some guidance here? What to look for? What may cause this problem?
Thanks in advance.
Accepted answer
On this particular user, are all the work assignments unbounded ? (no date relating to any assignment)