Roll up to second level plan items is not done in Eclipse Plan Editor


Aradhya K (1.4k44345) | asked Dec 06 '12, 12:37 p.m.
JAZZ DEVELOPER
 Create a Scrum Project.
Open a Plan in the Eclipse client
Create the below Heirarchy

Story_top
Task a 1 week
Story_child
Task b 1 week
Task c 1 week

You can see that the progress till the Story_child shows 0/80 hours
But the progress at the Story_top shows 0/0

The Web client is able to roll up the hours correctly, the problem happens only on the Eclipse client.

One answer



permanent link
Aradhya K (1.4k44345) | answered Dec 06 '12, 12:38 p.m.
JAZZ DEVELOPER

Your answer