It's all about the answers!

Ask a question

Progress bar not rendering the Behind by values correctly on Eclipse client


Aradhya K (1.4k54345) | asked Oct 18 '12, 1:37 a.m.
JAZZ DEVELOPER
1) Open up project area with OOTB process template scrum
2) Create work item of type task, filed against the project area from 1) Set yourself as owner and plan for Sprint 1 (1.0).
3) Set Estimate as 10 hours
4) Adjust the iteration dates so that the progress is negative on the web client.
5) Open the Spring Backlog [Sprint 1 (1.0)] plan view in the RTC Eclipse client of 3.0.1.4 and 4.0.
Please check the image below for more info:
error in displaying behind by  values

One answer



permanent link
Aradhya K (1.4k54345) | answered Oct 18 '12, 1:39 a.m.
JAZZ DEVELOPER
This problem only exists in RTC 4.0 and 4.0.0.1.
Do migrate to 4.0.1. once available to get the fix for this problem.

Your answer


Register or to post your answer.