Create Full traceability report in CLM 4.0
Anurag Rajput (80●2●17●23)
| asked Sep 19 '12, 8:05 a.m.
edited Sep 19 '12, 10:53 a.m. by Seth Packham (1.4k●4●22●13)
I have created a requirement in RRC, assigned a work item for the same requirement in RTC and created Test cases for the same in RQM. Once the work item is tested and closed successfully. Is it possible to create full traceability report for the Flow of that particular requirement from RRC-RTC-RQM ?? If yes... How can we do it??
Thanks in Advance.
Regards,
Anurag Rajput
|
2 answers
Robin Bater (3.4k●4●7)
| answered Sep 19 '12, 9:37 a.m.
JAZZ DEVELOPER edited Sep 19 '12, 10:35 a.m.
There is also this CLM Reporting workshop that might help in understanding the RRDI and RRDG/RPE reporting options
https://jazz.net/library/article/675 Now from RRC you can create a view of your requirements and include the Implemented By, TrackedBy and ValidatedBy columns. This will show the requirement, the linked work item and test case and the status of each. Also there is a Traceability Report included in RRC. Comments
Anurag Rajput
commented Sep 25 '12, 12:28 a.m.
Hi Robin, Thanks a lot for your help Regards, Anurag Rajput |
Anurag,
Creating a full tranceability report will require using at least CLM 3.0.1. You will need to setup the shared data warehouse and RRDI. I believe the RQM app already ships with some RRDI traceability reports. I will let someone from RQM answer which ones are those. |