Nicolás Rodríguez (3142125) | asked Sep 13 '12, 7:33 p.m.
Hi!

I´m trying to put read only property in a duration attribute, i already tried many ways.

This field  is synchronized with the timesheet for the timespent sum result hours, so if I put it as reading through behaviors or through modification workitems permissions with the process configuration options, it generate error because the field is filled automatic.

Also try to do so by the Presentation Editor but Time Spent not come out with the same properties as if it were other attribute type.

TimeSpent:

Does someone know in the properties section, how can a put readonly value?



Comments
Nicolás Rodríguez commented Sep 13 '12, 7:37 p.m.

Excuse me, is DURATION (TIMESPENT)

One answer



permanent link
Takehiko Amano (1.3k3741) | answered Sep 13 '12, 8:16 p.m.
JAZZ DEVELOPER
If I understand your question correctly, here is a way to turn off sync "time spent" attribute with time sheet in traditional process template.

http://pic.dhe.ibm.com/infocenter/clmhelp/v4r0/topic/com.ibm.jazz.platform.doc/topics/t_sync_timespent_timetracking_ecp.html