How to traverse work items programmatically?


Mirco Hering (1123) | asked Aug 13 '12, 4:44 p.m.

Hi there,

I am building functionality that will only accept changeset associated with completed stories into a controlled workspace. The WI structure is Story->Task->ChangeSet.

Now to the above i need to identify for each candidate ChangeSet the associated Story and check the status. I was not yet able to find out how to traverse the hierarchy programmtically. Can anyone please help?

Thanks,
    Mirco

One answer



permanent link
Ralph Schoon (63.1k33645) | answered Aug 13 '12, 4:57 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
This could be a starter: https://rsjazz.wordpress.com/2012/07/31/rtc-update-parent-duration-estimation-and-effort-participant/