It's all about the answers!

Ask a question

Work Item bleeding per iteration


Aaron Cohen (8207851) | asked Aug 08 '12, 4:59 p.m.
JAZZ DEVELOPER
edited Aug 08 '12, 7:14 p.m. by Jared Burns (4.5k29)
Rational Team Concert has the ability to report on the # of Work Items that have been deferred. I have a manager who needs the number of work items that have been moved to a later iteration broken down by owner. How should I best report on this metric? Is this available in an existing RTC or Insight report? majority of the RTC reports are broken down by team not owner. 

Thank you!

One answer



permanent link
Sterling Ferguson-II (1.6k8280269) | answered Aug 08 '12, 6:28 p.m.
 My previous job wanted this from ClearQuest. They had to settle for exports and manipulation to create excel reports. If you create an enhancement for RRDI or Insight, post it here. I'll subscribe...

Your answer


Register or to post your answer.