How to handle Shared/Part-time Resources?

For shared or part-time resources, there should be a possibility to define an availability percentage for each team the user is participating in. In the time-boxing view, the length of the item boxes should visualize the days the assigned resource will need for this task.
For example, an item that is estimated with 2 days of work should be shown as 4 implementation days, if assigned to a resource that is available only 50% for the specific team.

0 votes



2 answers

Permanent link
Hallo Michael,

sound to me that we should follow-up the planning of preallocated time via https://jazz.net/forums/viewtopic.php?t=164.

Thanks for the information and kind regards, Markus

Hi Markus,

it is planned to address this issue when we implement the work time
management as described in https://jazz.net/forums/viewtopic.php?t=164.
We intend to implement a solution just the way you described it.

Thanks,
MikeS

mschille wrote:
For shared or part-time resources, there should be a possibility to
define an availability percentage for each team the user is
participating in. In the time-boxing view, the length of the item
boxes should visualize the days the assigned resource will need for
this task.
For example, an item that is estimated with 2 days of work should be
shown as 4 implementation days, if assigned to a resource that is
available only 50% for the specific team.

0 votes


Permanent link
Hi Markus,

it is planned to address this issue when we implement the work time
management as described in https://jazz.net/forums/viewtopic.php?t=164.
We intend to implement a solution just the way you described it.

Thanks,
MikeS

mschille wrote:
For shared or part-time resources, there should be a possibility to
define an availability percentage for each team the user is
participating in. In the time-boxing view, the length of the item
boxes should visualize the days the assigned resource will need for
this task.
For example, an item that is estimated with 2 days of work should be
shown as 4 implementation days, if assigned to a resource that is
available only 50% for the specific team.

0 votes

Your answer

Register or log in to post your answer.

Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.

Search context
Follow this question

By Email: 

Once you sign in you will be able to subscribe for any updates here.

By RSS:

Answers
Answers and Comments
Question details

Question asked: Jul 05 '07, 6:08 a.m.

Question was seen: 7,804 times

Last updated: Jul 05 '07, 6:08 a.m.

Confirmation Cancel Confirm