How to handle Shared/Part-time Resources?
For shared or part-time resources, there should be a possibility to define an availability percentage for each team the user is participating in. In the time-boxing view, the length of the item boxes should visualize the days the assigned resource will need for this task.
For example, an item that is estimated with 2 days of work should be shown as 4 implementation days, if assigned to a resource that is available only 50% for the specific team.
For example, an item that is estimated with 2 days of work should be shown as 4 implementation days, if assigned to a resource that is available only 50% for the specific team.
2 answers
Hallo Michael,
sound to me that we should follow-up the planning of preallocated time via https://jazz.net/forums/viewtopic.php?t=164.
Thanks for the information and kind regards, Markus
sound to me that we should follow-up the planning of preallocated time via https://jazz.net/forums/viewtopic.php?t=164.
Thanks for the information and kind regards, Markus
Hi Markus,
it is planned to address this issue when we implement the work time
management as described in https://jazz.net/forums/viewtopic.php?t=164.
We intend to implement a solution just the way you described it.
Thanks,
MikeS
mschille wrote:
For shared or part-time resources, there should be a possibility to
define an availability percentage for each team the user is
participating in. In the time-boxing view, the length of the item
boxes should visualize the days the assigned resource will need for
this task.
For example, an item that is estimated with 2 days of work should be
shown as 4 implementation days, if assigned to a resource that is
available only 50% for the specific team.
Hi Markus,
it is planned to address this issue when we implement the work time
management as described in https://jazz.net/forums/viewtopic.php?t=164.
We intend to implement a solution just the way you described it.
Thanks,
MikeS
mschille wrote:
it is planned to address this issue when we implement the work time
management as described in https://jazz.net/forums/viewtopic.php?t=164.
We intend to implement a solution just the way you described it.
Thanks,
MikeS
mschille wrote:
For shared or part-time resources, there should be a possibility to
define an availability percentage for each team the user is
participating in. In the time-boxing view, the length of the item
boxes should visualize the days the assigned resource will need for
this task.
For example, an item that is estimated with 2 days of work should be
shown as 4 implementation days, if assigned to a resource that is
available only 50% for the specific team.