Help for "Estimating multiple tasks"
We made a template with this structure: Requirement and linked tasks. The thing is that we have about 50 tasks and we have to estimate all of them. Nowadays, with this structure (template), we have to estimate one by one all this tasks.
My question is: There is another way to do that, instead of to estimate one by one all those tasks ? Also, we would like totalize the result of the estimation in one field (Integer) of the Requirement. This is posible ? Thanks for your help |
3 answers
Geoffrey Clemm (30.1k●3●30●35)
| answered Aug 23 '11, 4:39 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
In RTC-3.0.1, in the web browser UI, you can use the "edit multiple work
items" operation ... multi-select all of the work items, and change the estimate of all of them in one request. Cheers, Geoff On 8/23/2011 2:53 PM, mtorres wrote: We made a template with this structure: Requirement and linked tasks. |
Thanks so much Geoff.
Question: Can I do this in RTC 3.0 ? Or I have to update the version ? |
Geoffrey Clemm (30.1k●3●30●35)
| answered Aug 30 '11, 7:14 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
If you don't see the "edit multiple work items" action in your 3.0 web
browser, then you probably do need to upgrade. Cheers, Geoff On 8/29/2011 9:53 AM, mtorres wrote: Thanks so much Geoff. |
Your answer