Does anyone know if the following is possible;
Is there a mechanism to monitor workload for a user across projects or does this only work across team areas? i.e. T = Team area Repository / \ / \ Project A Project B / \ / \ T1 T2 T1 T2 | | \ user1 user1 user1 So will the work assigned to user1 be able to be seen over both projects? |
2 answers
Hi,
I would expect that, depending on what you mean by 'workload', the information you need should be in the data warehouse, and you can write reports in RRDI that aggregate this data across project areas. (The limitation is that the data warehouse is associated with a JTS, so while you can do cross-project and cross-application reports, this is only true for apps that are connected to the same JTS).
The warehouse stores work items, owners, estimates, time spent, team areas and project areas, so a rough guess on my part says your workload calculation should be possible.
james
Comments Looking at https://jazz.net/library/article/586, "Load Information is a comparison of remaining work time (as defined in the work environment) and remaining estimated work." .
|
Thanks James. I was looking for data on percentage allocation to team areas, but thinking about your answer maybe I don't need that information.
|
Your answer
Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.
Comments
Looks like this isn't possible. Wonder if It's possible via RRDI?