Hi Folks
Is there anyway to determine the dependency relationship for a given change set without actually deliver/accepting it? Basically I'm trying to assess the merge effort prior to actually performing it. regards /anders |
3 answers
Hi David
We're on 4.0.6 and I'm thrilled by the merge improvements.
We cannot move to 5.0 as don't have a SQL Server 2012 and 2014 isn't supported by 5.0 though.
I still think some visualization of the changeset dependency would be useful.
From a long history of changes I'd like to have an indication on exactly which changes I should accept to get the cleanest merge.
I imagine something along these lines:
At this point I'll then unselect cs29 choose to fill in the gap for that changeset to complete my merge.
What do you think?
/anders
Comments
David Lafreniere
commented Jul 02 '14, 10:36 a.m.
| edited Jul 02 '14, 11:05 a.m.
FORUM MODERATOR / JAZZ DEVELOPER
I agree it would be nice to have some visualization of the change sets that fill the gap. However nothing can be done in 4.0.6 to support that. We released some pretty complicated changes of the internal workings of SCM in 5.0. These changes enable a few features, one of which was the ability to easily identify the change sets that fill the gap (which was also added for 5.0).
Also, the use case where the end goal is to reduce the merge effort sounds a little strange to me personally, or at least I have not heard of that request specifically.
David Lafreniere
commented Jul 02 '14, 11:04 a.m.
| edited Jul 02 '14, 11:04 a.m.
FORUM MODERATOR / JAZZ DEVELOPER
The other more rare case would be to decide at that point you want Feature X and and a subset of the other stuff, say Feature C. Since you made the decision, it doesn't matter how complicated the merge is, it must be done... So you select what you want, choose to 'not' fill the gap, and continue merging in the Gap editor which was delivered in RTC 4.0.6. However we urge anyone who does fill the gap or cherry-picks from the change sets in the gap, to ask themselves why was the decision to accept or back/forward port those features / fixes was not done before hand (i.e why were they not in the initial selection in the first place?).
Also, the most common use case I've seen for completely filling the gap, would be cases in which the user wants to do something quick and temporary, without flowing those changes to any development/integration streams. Ex: If developerA wants to review a feature that developerB was doing, developerA can change the flow target of their repository workspace to developerB's repository workspace, they can then accept the change sets for that feature (or without changing flow targets, perhaps accept change sets directly from a work item). If there are gaps, they don't care what other features or fixes get brought in, they just want to accept everything so they can get in a state which they can compile everything and test out the feature they want to test, once they are done, they likely will discard all the change sets they brought in. |
I agree with what Geoffrey said. Just accept the change set, and see what the conflicts look like.
If you decide you don't want to merge now, just suspend or discard the change set. This will also let you know if gaps are involved. It can also let you get an idea of how much merging is required if you want to merge just the selected change set(s), and will also give you an idea of how many change sets fill the gap (which also may result in conflicts after accepting). This all depends on which RTC version you are using however. In RTC 4.0.5 we delivered additional support when trying to accept change sets which have a gap (often encountered when trying to backport fixes). In a very brief summary of the feature, when you accept change sets with a gap, you can now follow a gap workflow that accepts one change set at a time and, for change sets that contain gaps, creates a new change set (with aided traceability), that contains the equivalent changes. This means users will not have to accept the change sets 'as a patch'. Applying change sets as a patch has limitations compared to the new workflow (as discussed in the article below). This feature is summarized in the RTC 4.0.5 'New & Noteworthy' page: https://jazz.net/downloads/rational-team-concert/releases/4.0.5?p=news#scm-improve-usability-405-m1 Below are some videos which show this feature: -Accepting multiple change sets with gaps in the RTC 4.0.5 client for Eclipse IDE: https://www.youtube.com/watch?v=28raag5RdzU -Accepting a change set with a gap in the RTC 4.0.5 client for Eclipse IDE: https://www.youtube.com/watch?v=TucVu_BgB7E In RTC 5.0 we added a "fill the gap" feature where the change sets that fill the gap are shown to the user, allowing them to either accept all the change sets or to continue with the gap workflow that was available in RTC 4.0.5. This feature is summarized in the RTC 5.0 'New & Noteworthy' page: https://jazz.net/downloads/rational-team-concert/releases/5.0?p=news#eclipse-fill-gaps The classes that are involved for filling the gap include (available in RTC 5.0): client side: IWorkspaceConnection.findChangeSetsToAcceptToFillGap(...) server side: IScmQueryService.findChangeSetsToAcceptToFillGap(...) Both features are explained in detail in the "Improved Gap Handling for SCM" article: https://jazz.net/library/article/1372 |
Geoffrey Clemm (30.1k●3●30●35)
| answered Apr 14 '11, 9:48 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Just accept the change set, and see what the conflicts look like.
If you decide you don't want to merge now, just suspend or discard the change set. Cheers, Geoff On 4/14/2011 8:53 AM, atruelsen wrote: Hi Folks |