Work Item Planned Start and End Dates Always "None&quot


Manohar Rao (2211116) | asked Mar 29 '11, 2:42 p.m.
In the RTC 3.0 web client, I have work items planned for an Iteration. The Iteration has Start and End Dates. The work item has an Estimate.

However, the Planned Start and Planned End Dates for the work item are never populated with any dates. I'd have thought these fields would be derived from the plan start date and the estimate. In fact, even the Gantt chart view shows when this work item will start and end.

Is there any other setting I need to check for to get these fields populated? Also, is there any way to manually enter values in the Planned Start and End Date fields for a work item?

My project is based on the Formal Process Management Process template, and I'm using the web client.

Thanks

2 answers



permanent link
Claudia Callegari (44449871) | answered Apr 12 '11, 8:33 a.m.
Thanks Chethna! I was experiencing the same problem and after taking the snapshot it looks fine. Beautiful.
--Claudia

permanent link
Chethna Shenoy (3644) | answered Apr 08 '11, 3:39 p.m.
JAZZ DEVELOPER
Have you created a snapshot? Please create a snapshot of type Planned.

Regards,
Chethna Shenoy