It's all about the answers!

Ask a question

Eliminating requirement for defect estimates?


Michael Harris (2114) | asked Sep 16 '10, 12:14 p.m.
When we open our plans, we get a message that there are "problems detected" and all our defects show up with a warning yellow triangle by them. The warning is "The work item is planned but has no estimate specified."

We are not putting estimates in our defects. How do we configure RTC to eliminate this message and eliminate the requirement for an estimate on a defect?

3 answers



permanent link
Geoffrey Clemm (30.1k33035) | answered Sep 17 '10, 3:48 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Just thinking out loud ... you can contribute process actions on "save
work item" ... so if your process action initialized the estimate to
some standard value, then you wouldn't get the warning.

Alternatively, you could periodically just run a query that selects all
defects that don't have an estimate, multi-select them all, and set an
estimate on all of them.

Cheers,
Geoff

On 9/17/2010 12:38 PM, harrismd wrote:
We only measure progress by total number of defects fixed. Decisions
about whether a defect goes into the current iteration backlog is
done based upon a gut feeling and whether or not it is considered
"must fix". The decision has no real basis in if it is
actually possible to fix the defect in the iteration. At the end of
the iteration, whatever defects didn't get fixed, they're simply
dumped in the next iteration backlog. No, it's not SCRUM, but it's
where we are. If we took the time to investigate the defect enough
to have an accurate estimate, most times we could have already fixed
it.

Do we just have to learn to ignore the warnings?

permanent link
Michael Harris (2114) | answered Sep 17 '10, 12:36 p.m.
We only measure progress by total number of defects fixed. Decisions about whether a defect goes into the current iteration backlog is done based upon a gut feeling and whether or not it is considered "must fix". The decision has no real basis in if it is actually possible to fix the defect in the iteration. At the end of the iteration, whatever defects didn't get fixed, they're simply dumped in the next iteration backlog. No, it's not SCRUM, but it's where we are. If we took the time to investigate the defect enough to have an accurate estimate, most times we could have already fixed it.

Do we just have to learn to ignore the warnings?

permanent link
Geoffrey Clemm (30.1k33035) | answered Sep 16 '10, 10:30 p.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
If you aren't putting estimates on your defects, how do you track and
measure progress against your defect backlog?

Cheers,
Geoff

On 9/16/2010 12:23 PM, harrismd wrote:
When we open our plans, we get a message that there are "problems
detected" and all our defects show up with a warning yellow
triangle by them. The warning is "The work item is planned but
has no estimate specified."

We are not putting estimates in our defects. How do we configure RTC
to eliminate this message and eliminate the requirement for an
estimate on a defect?

Your answer


Register or to post your answer.


Dashboards and work items are no longer publicly available, so some links may be invalid. We now provide similar information through other means. Learn more here.