How to make Time Remaining calculated automatically
Hi -
I have 3 Attributes in RTC 2.0 Task type Workitems We find good to fill Estimate and Due Date as this is one time task where as for Time Remaining - we have to update regularly which is pain to team. Management wants to see current progress - in case team fails to update Time Remaining, Project Progress report shows incorrect data. Could you please let me know how to make Time Remaining attribute calculated automatically with the formula Thanks and Regards - Perala |
One answer
Hello,
I think with a script in the Attribute Customization this could be possible. Whereby I would have a concern to calculate this value, because it will never show the correct progress and therefore the reporting will be not showing the current status but the one that would be liked to be shown. Siegfried |