Problems with user absences planning


Robert Farrugia (5614) | asked Jan 28 '08, 4:28 a.m.
Hi Im using beta 2. When i try to insert an absence, within the user properties, im getting an error when i change the dates.. for instance if i would like an absence between 14th feb 2008 and 18th february 2008 i get an error : ENTER A VALID START DATE!... the only time i dont get an error is when i leave the start and end date unchanged...

4 answers



permanent link
Tobias Widmer (3211) | answered Jan 30 '08, 4:48 a.m.
farrugiarobert schrieb:
Hi

I Opened Defect 42757

Have you encountered the problem before? what do you think the problem
might be?

Regards

Robert

Hi,


No, I haven't encountered it before. I believe it's a NumberFormat which
is not initialized with the correct locale.

Cheers,
Tobias

Jazz Coverage, Collaboration, Agile Planning

permanent link
Robert Farrugia (5614) | answered Jan 28 '08, 8:40 a.m.
Hi

I Opened Defect 42757

Have you encountered the problem before? what do you think the problem might be?

Regards

Robert

permanent link
Tobias Widmer (3211) | answered Jan 28 '08, 6:38 a.m.
farrugiarobert schrieb:
Hi Im using beta 2. When i try to insert an absence, within the user
properties, im getting an error when i change the dates.. for
instance if i would like an absence between 14th feb 2008 and 18th
february 2008 i get an error : ENTER A VALID START DATE!... the only
time i dont get an error is when i leave the start and end date
unchanged...


Hi Robert,

Could you please file a bug report with exact steps to reproduce? It
would be interesting as well whether you have additional absences. You
should also indicate the date/time when you tried to change the absence.

Cheers,
Tobias

permanent link
Tobias Widmer (3211) | answered Jan 28 '08, 6:38 a.m.
farrugiarobert schrieb:
Hi Im using beta 2. When i try to insert an absence, within the user
properties, im getting an error when i change the dates.. for
instance if i would like an absence between 14th feb 2008 and 18th
february 2008 i get an error : ENTER A VALID START DATE!... the only
time i dont get an error is when i leave the start and end date
unchanged...


Please file the bug report against Agile Planning and subscribe me.

Cheers,

Tobias
Jazz Collaboration, Coverage, Agile Planning team.