Error in upgrading DNG from CLM6.0.6.1 to ELM 7.0.2
Hello,
On DNG when we ran the upgrade command, In Export link Validity data command it says as below. <o:p> </o:p>
<o:p> </o:p>
CRJAZ1356E The repotools command could not connect to the following server ‘https://hostname.org.net:9443/jts’ <o:p> </o:p>
<o:p> (Same URL which we used in upgrade command) </o:p>
The rm upgrade failed at step 1. <o:p> </o:p>
<o:p> </o:p> We followed the jazz.net link
<o:p> </o:p>
<o:p> </o:p>
“https://jazz.net/wiki/bin/view/Deployment/MigratingTheRequirementsManagementLinkValidityData%22 <o:p> </o:p>
<o:p> </o:p>
But still we were unable to cross the step. <o:p> </o:p>
Could anyone help on this.
Thanks,
Sunil Deshapnde
Accepted answer
Sunil,
One other answer
Sunil,