Tasks replanning automatically in RTC upon parent task planned dates
![]() I have a scenario where the Release plan has 10 tasks with their planned dates from Feb 17th to March 25th (excluding Weekends). On 5th March , I could complete only 3 tasks and still 7 tasks are pending to complete. At this point, the Release plan is put ON HOLD. After 1 week, the project is resuming on 15th March. So all my remaining 7 tasks has to be replanned starting from 15th March since my old dates are no more valid. <o:p> </o:p> <o:p> </o:p> In this scenario, will RTC automatically replans these remaining tasks (5,6,7,8,9,10) if I plan the 4th tasks starting from 15th March? <o:p> </o:p> |
3 answers
![]()
Ralph Schoon (62.0k●3●36●43)
| answered Feb 19 '20, 3:12 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER There is no planning capability that would support any automation on the due date. If you think there should be one, feel free to create an enhancement request.
|
![]() So how do we handle this scenario? i think this use case is not very uncommon like tasks going on hold sometimes and replanning the Due Dates to a new date, etc |
![]()
Ralph Schoon (62.0k●3●36●43)
| answered Feb 18 '20, 2:17 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER edited Feb 18 '20, 2:18 a.m.
As far as I can tell, the dates are dynamically planned based on the current data/time, the planned for iteration, the allocation of users etc. So I am not sure what you are asking.
Also RTC is not MS Project and, other than creating plan snapshots, there is no "replanning".
|
Comments
any pointers for this please