Can a Team have more than one timeline
- I'm using a RTC project area as a container for work items related to an organizational unit.
- Within the project area, several projects are represented as different RTC-timelines.
- The RTC-teams are arranged in a way that they represent the different department's of the organizational unit.
- For each project several departments provide one or more team members to a project (RTC timeline). (Typically for a Matrix organization)
-
The Categories have a 1:1 mapping to the teams. (e.g. Category A <-> Team A, Category B <-> Team B ...)
The idea behind is to file work items against a team (by choosing the category in Filed Against field) and to also assign the work item to a project by choosing the iteration of a Timeline in the Planned For field.
PROBLEM: For this configuration the team (department) do not belong to only one timeline (project), because the department provides stuff to different projects. Therefore I would like to assign the department team to different projects (RTC-timelines) which is not possible with RTC.
How shall i handle this conflict?
Is there a possibility to assign a team to more than one timeline?
Accepted answer
No, any process area can only ever be associated to one timeline: https://jazz.net/wiki/bin/view/Deployment/RTCProcessFundamentals#Timelines .
If the configuration team wants to manage their time, they need their own timeline or use a, timeline that exists. This way they can be allocated to that team and you can use planning and estimations.
Or you make the members of the conf team member of each other area with a percentage of allocation to that team.This way the users would be in many teams and have their work planned with a percentage. E.g. a 1 hour Job would be planned to take 6 hours if you have 6 teams and are allocated with 10%.
This can not be changed, all planning and estimations depend on this.
I would suggest solution 1 because that is easier to handle for the department team.