Importing CSV into a backlog and creating a iteration with the results


Mark Jones (111) | asked Apr 24 '19, 2:46 p.m.
edited Apr 24 '19, 3:35 p.m.

Hello I have 3 a questions about importing a CSV into RTC.

Where does it go?

How can I pull my imported items into an Iteration?

How do I move items from a Backlog into a Plan?

 Thanks Mark

One answer



permanent link
Ralph Schoon (63.1k33646) | answered Apr 25 '19, 9:54 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
edited Apr 25 '19, 10:38 a.m.
I would suggest to try to understand the basic concepts of RTC: https://jazz.net/wiki/bin/view/Deployment/RTCProcessFundamentals


  1. The CSV is going nowhere. The contained data is used to create work items.
  2. The "Planned for" attribute must be set to an iteration, during the import or afterwards.
  3. A backlog is also a plan. To plan them for a different iteration, change the "Planned For" attribute. The Category "Filed against" is also important.