It's all about the answers!

Ask a question

Is there any way to check in task attachments into source control RTC?


Sneha B (1339) | asked Jun 22 '18, 10:30 a.m.

 Is there any way/automation scripts using which I can load all the attachments which are present in the work items (tasks/defects) and upload to the RTC source control repository?

One answer



permanent link
Ralph Schoon (63.1k33645) | answered Jun 22 '18, 10:43 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER

No.

Plus it is not a good idea to have all these binaries in the SCM system. You would rather want to put them into an artifact repository. This is also not yet supported. There are requests to make that possible.