How to move a project area data (including history) from one RTC server to another?


deepti harinkhede (217) | asked May 04 '18, 4:47 a.m.

Hi There,

We need to move some project areas (including workitems, history, plans etc.) from RTC UAT to RTC Prod. Is there a way to achieve this?

Thanks,

Dipti

One answer



permanent link
Kenji Sarai (96029) | answered May 07 '18, 2:04 a.m.

Hi Deepti,

You can do so by database backup and restore. History will be retained.
However, all projects are migrated. You cannot select some of them. You may archive projects which are not necessary, but archived data is still in the database.