Can I have two parallel release iterations established as current in my timeline?


dislevis palma (111) | asked Mar 15 '18, 11:44 a.m.
edited Mar 20 '18, 7:10 a.m. by Geoffrey Clemm (30.1k33035)

Hello everyone, can I have two parallel release iterations established as current in my timeline? 

Thanks for your comments. 
 :-)


Comments
Donald Nong commented Mar 15 '18, 10:34 p.m.

English only, please.


Ralph Schoon commented Mar 16 '18, 3:11 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER

I close this question. this is an English speaking community. Please restate your question in English.

One answer



permanent link
Geoffrey Clemm (30.1k33035) | answered Mar 20 '18, 7:12 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER

I went ahead and translated to English, and re-opened.

The answer is that no, you cannot have two parallel iterations marked as current in the same timeline.
The reason is that the current iteration can affect the process, and if there were two parallel iterations marked as current, the process would be ambiguous.