User Story Total Time Spent


Sabrina Moody (132) | asked Feb 14 '18, 9:34 a.m.

Is it possible that a user story can calculate the total time spent from all tasks under that story?

One answer



permanent link
Ralph Schoon (63.1k33645) | answered Feb 14 '18, 9:48 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
edited Feb 15 '18, 7:42 a.m.

There is support for this out of the box in the planning component provided the Story and the children are in the same project area.


Comments
Sabrina Moody commented Feb 14 '18, 12:04 p.m.

The user story and children are in the same project area; but users are wanting the user story to calculate total time spent by the tasks(children) automatically.  Right now, we have to figure time spent manually by adding all the time spent in each task and putting in user story.


Sabrina Moody commented Feb 14 '18, 3:41 p.m.

How would we go about setting this up in RTC to handle this way?


Ralph Schoon commented Feb 15 '18, 7:41 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER

There is nothing to configure. This is out of the box as far as I can tell. If you use one of the agile templates (probably even otherwise) There is a roll-up mechanism implemented that looks at the estimate, time spent/remaining, correction in execution items and rolls the data up to the plan items such as Stories and Epics..

Work Items have not attribute based Progress presentation that show rolled up story points and hours in the work item. The same data can be seen in hierarchical plan views.

Here the plan


Here the work item editor presentation


 
In the example 0/96 hours is due to no work being done in any of the child work items.


Sabrina Moody commented Mar 06 '19, 10:08 a.m.

We don't have progress on our User Story; we have time spent.


Ralph Schoon commented Mar 06 '19, 10:25 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
Then someone likely accidentally unchecked the Story in the Plan Work Item Categorization.


 