What am I supposed to do with current iteration ?


Hugh Cnn (19111) | asked Jul 25 '17, 8:00 a.m.

Hi everybody,

I am using RTC5 and I sw that we can put an iteration as current iteration. I am looking for what is that for... Can anyone help me please ?

Thanks,

H

Accepted answer


permanent link
Ulf Arne Bister (1.3k413) | answered Jul 25 '17, 9:08 a.m.

Hugh,

permissions in the process configuration can also be set against iterations. You can e.g. have iterations solely for the purpose of generally switching on / off certain process constraints ("delivery only after approval by tech lead") when setting the iteration current. See also
https://jazz.net/help-dev/clm/index.jsp?topic=%2Fcom.ibm.jazz.platform.doc%2Ftopics%2Ft_customizing_permissions_time_period.html

If this is helpful please mark the answer as accepted.

- Arne

Hugh Cnn selected this answer as the correct answer

Comments
Hugh Cnn commented Jul 25 '17, 10:20 a.m.

Thanks Arne

One other answer



permanent link
Geoffrey Clemm (30.1k33035) | answered Jul 26 '17, 3:06 a.m.
FORUM ADMINISTRATOR / FORUM MODERATOR / JAZZ DEVELOPER
edited Jul 26 '17, 3:06 a.m.

 Arne's answer is a major reason, but some other reasons include:

- The current iteration can be used when construction queries, and is used in many of the out-of-the-box queries.
- The current iteration can be used in JRS queries.
- There are some dashboard widgets, such as the Timelines widget that are affected by the current iteration ( https://jazz.net/help-dev/clm/index.jsp?topic=%2Fcom.ibm.jazz.dashboard.doc%2Ftopics%2Fc_widget_types.html )
- There are some menus that mark which is the current iteration (such as the menu for selecting a value for the Planned-For property of a work item).
- A pre-condition can reference the current iteration (example: the built-in Descriptive_Change_Sets Deliver pre-condition).
- The "current work"  in the Eclipse MyWork view determines current work from the current iteration.